2015 TH 3 and Third Street Improvements

INTRODUCTION



The 2015 Trunk Highway 3 and Third Street Improvements Project is designed to provide a safe at-grade crossing of Trunk Highway 3. Improvements include a Rapid Rectangular Flashing Beacon (RRFB), center medians, and islands to channelize traffic from both directions on Third Street.


PROJECT MEETINGS



  • 8/26/15- Project update letter sent to adjacent businesses:

    Update Letter (PDF)

  • 8/18/15 Reject Bid, City Council direction to work with MnDOT and re-bid project with Trunk Highway 3 North overlay scheduled for summer of 2016
  • 8/6/15 Bid Opening
  • 7/7/15 Approve Plans and Order Advertisement for Bids
  • 3/3/15 Order Preparation of Plans and Specifications
  • 2/4/15 Neighborhood Meeting

PROJECT UPDATES




MAPS/PLANS/FILES