4th Street East Improvements (2010 Construction)

Project Process

Date1

Project Step            

Purpose of step

Council Action2

July 6, 2009

Approve initiation of project (This step will be used until CIP is a complete developed document) and Authorize staff to request proposals for engineering services.

Notifies staff that project should move forward to the feasibility stage. This includes preparing a request for proposals for engineering services, evaluation of the submitted proposals for best value of services, and preparing a contract for council consideration. Note that professional services contracts are not required to go through the bidding process.

Motion

August 2009

Meet with Streetscape Task Force #1

 

 

Sept. 15, 2009

RFP

 

 

Sept. 28, 2009

Engineering Proposals Due

 

 

October 5, 2009

Order Preparation of Feasibility Report and award engineering services contract

Ordering of the feasibility report is a required step of 429 process (see table below). Staff intends to use an outside consultant to supplement current staffing levels.

Resolution 2009-098
(429)

October 13, 2009

Forester Report

A trained forester or arborist will evaluate the trees along the project corridor and give recommendations for project considerations.

 

October 22, 2009

Hold First Neighborhood Meeting

The intent of this meeting will be to inform the neighborhood of the upcoming project and seek input on improvements.  Input will be summarized and given to council.

 

October 2009

Draft Feasibility Report

 

 

Nov. 5, 2009

Second Neighborhood Meeting

Present a draft of the feasibility report to the neighborhood for input prior to action by council.

 

Nov. 16, 2009

Accept feasibility and call for Public Hearing

The engineer will present the proposed project including a cost estimate and potential assessments

Resolution
2009-112, 2009-113, 2009-114
(429)

Nov. 19, 2009

Meet with Streetscape Task Force #2

 

 

Oct/Nov 2009

Tour Potential Project Area with Council

Walk project area to make Council aware of potential controversial issues such as sidewalk placement and tree removals.

 

Dec. 21, 2009

Public Hearing on Improvements

The purpose of the first hearing is for the council to discuss a specific local improvement before ordering it done. The council considers all the information in the feasibility report and any other information necessary for council deliberation.

At the improvement hearing, interested persons may voice their concerns, whether or not they are in the proposed assessment area. A reasonable estimate of the total amount to be assessed and a description of the methodology used to calculate individual assessments for affected parcels must be available at the hearing. If the council rejects the project, it may not reconsider that same project unless another hearing is held following the required notice.

Public Hearing (429)

Jan. 4, 2010

Order Improvement and Preparation of Plans and Specifications

The project may be ordered any time within 6 months after the improvement hearing.  It is not advised to change project parameters after ordering the improvement.  Upon ordering the improvement construction drawings and specifications are prepared.  Any changes to the project parameters after this point will cause a redesign costing additional money for engineering services and staff time and causing a delay of the project.

Resolution
2010-003
(429)

Mar. 12, 2009 State Aid Review Submit Plans to State Aid for review and approval  

Mar. 15. 2010

Third Neighborhood Meeting

Present the detailed plans and specifications to the neighborhood for input prior to council action.

 

Mar. 16, 2010

Approve Plans and order advertisement for bids (Pending State Aid Approval)

This step is a requirement of the 429 process.

Proposed
Resolution
2010-023
(429)

Apr. 20, 2010

Accept bids and award contract

This step is a requirement of the 429 process and allows staff to move forward with the construction process.

Resolution (429)

April/May 2010

Neighborhood Tour & Individual Property Owner Meetings

Prior to the start of construction a walking tour of the project corridor will be taken meeting one-on-one with owners and residents to go over the details of construction, try to address concerns, and document existing conditions as necessary.

 

Substantial
May-Nov. 2010

Final
June 2011

PROJECT CONSTRUCTION

Once the project is awarded staff manages the day-to-day operations.  Typically a Resident Project Representative is on-site to make sure the project is constructed in accordance to the plans and specifications.  Communications between the contractor and City is limited to the Engineer and Resident Project Representative.  Significant changes would be brought to council for approval prior to the work being completed.  Minor change orders and field directives are authorized by the Engineer to maintain project construction and schedules.  All changes to the contract must be approved by council.  Minor changes which occurs during project final acceptance.

 

June 2011

Accept Improvements and Authorize Final Payment

The city engineer recommends to the council when final payment should be made to the contractor. The city council may accept the work by resolution. However, if the city fails to pay the amount due within 30 days of a monthly estimate, or 90 days after the final estimate, the city must pay interest on the past due amount as prescribed by law.

Resolution (429)

The following actions are also required by the 429 process to assess benefiting property owners for the cost of the local improvement.  These actions may be taken concurrently with the actions above.

Date1

Project Step

Purpose of step

Council Action2

November 2009

Appraisal Report

Based on the City’s new assessment policy, an appraisal of the project will be completed to determine the assessment rates.

 

Nov. 16, 2009

Set date and time of Assessment Hearing

Best practice suggests cities pass a resolution setting the date and time of the assessment hearing and directing that the city clerk publish and mail notice about the assessment hearing.

Resolution
2009-114
(429)

Dec. 21, 2009

Assessment Hearing

The purpose of the second hearing, commonly known as the assessment hearing, is to give property owners an opportunity to express concerns about the actual special assessment.  At the assessment hearing the council shall hear and consider all objections to the proposed assessment, whether presented orally or in writing.

Public Hearing
(429)

April 20, 2010

Adopt Assessment

The council has some flexibility before it adopts the assessment roll and may change, or amend, the proposed assessment as to any parcel. Council must, by resolution, adopt the same as the special assessment against the lands named in the assessment roll. Once the assessment roll is adopted the assessments are set and become liens against the properties listed.

Resolution (429)

1 – Dates in bold text denote actions or events that have taken place.  Dates in italics denote tentatively scheduled actions or events. 
2 – A motion will be used for those items that are not necessary for the 429 assessment process.  Resolutions are required for those steps that are part of the 429 process.

 


Web Development by Livefront, a Minneapolis Web Design firm.