Introduction

City Staff recommended to the Council in August 2010 that Linden St N and Plum St N from Saint Olaf Ave to Greenvale Ave and Second St W from Lincoln St to the dead-end undergo a complete reconstruction of the water and sewer lines, road subgrade and surface, curbs and sidewalks (see map of the approved project corridor). As a local city street the funding for the reconstruction will come from Northfield city funds. Upgrades to the main lines of the water, sanitary sewer, and storm sewer systems are paid through their respective city enterprise utility funds. The remainder of funding comes from bonding and special assessments of properties along the construction corridor.

Project Process

Most street reconstruction projects follow a standard procedure. While some dates may change as the project moves forward, the basic order of steps is maintained.

The process for developing the special assessments for properties along the project corridor follows state statutes (the so-called "429 Process"). The process steps are typically completed to take advantage of a positive bonding environment and to make full use of the construction season (May through November).

See the Project Process page for more details and dates of the project steps.

Email Notifications

If you live along the project corridor or are affected by the project you may sign up to receive email notices of project events such as public meetings, important construction dates, etc.

TIP: If the above link does not work or if you use web-based email, please send a message to engineering@ci.northfield.mn.us. Please insert "2011 Street Project Email" in the subject line and include your name, email address, and whether you would like to be added to or removed from our mailing list in the body of the message. This email notification list will be deleted at the end of the project.

Completed Phases

Information for Contractors

All bid documents for city projects are made available to the public through the city's eGramwebsite, except for the plan documents. Plans and sepcifications in digital format can be downloaded for free by registering for an eGram account with the city. Contractors must notify the city separately for each project to register for access to the documents for a specific project.

 

 