Water Tower Maintenance Project

Introduction

The City is completing maintenance on the City’s three water storage tanks. The major items of work being completed on the water storage tanks include:

  • Interior Tank Rehabilitation including spot repair and a protective coating system
  • Exterior Tank Rehabilitation including overcoat protective system
  • New City logos/lettering on exterior of tanks
  • New safety climb systems
  • Repair of concrete foundation
  • New pressure manway gaskets
  • New concrete splash pad

Project Timeline

Work will be completed over a three-year period with the following schedule:

  • Hall Avenue Tower – Oct. 1, 2019 or alternatively bid Oct. 1, 2020
  • South St. Olaf Ground Storage Tank – Oct. 1, 2020
  • North St. Olaf Ground Storage Tank – Oct. 1, 2021