2021 Reclamation and Overlay Project

NEIGHBORHOOD MEETING #1 PRESENTATION

FEASIBILITY REPORT

Questionnaire Results

Introduction

The 2021 Reclamation and Overlay Project includes:

  • Mayflower Drive from Parmeadow Drive to Turnberry Lane (Reclamation)
  • Parmeadow Drive from Mayflower Drive to Heywood Road (Reclamation)
  • Creek Lane from Mayflower Drive to Heywood Road (Reclamation)
  • Turnberry Lane from Mayflower Drive to Heywood Road (Reclamation)
  • Mayflower Hill Service Road (Reclamation)
  • Baneberry Court (Reclamation)
  • Mayflower Court (Reclamation)
  • Primrose Court (Reclamation)
  • Turnberry Court (Reclamation)
  • Goldenrod Court (Reclamation)
  • Goldenrod Circle (Reclamation)
  • Clover Court (Reclamation)
  • Crocus Court (Reclamation)
  • TH 3 east Frontage Road from Woodley Street to Jefferson Parkway (Mill and Overlay)
  • Jefferson Parkway from TH 3 to west dead end (Mill and Overlay)
  • Babcock Lane from TH 3 west frontage road to Babcock Park. (Mill and Overlay)
  • Bollenbacher Drive from Jefferson Parkway to west Frontage Road (Mill and Overlay)
  • Bollenbacher Court (Mill and Overlay)
  • West Frontage Road from Bollenbacher Drive to Riverview Drive (Mill and Overlay)

The process began with the Northfield City Council ordering a Feasibility Study on April 7, 2020. The Feasibility Study examines the proposed street and utility improvements along these street corridors to determine whether the project – as proposed – is feasible, cost effective and necessary.

Project process

The process for developing the special assessments for properties along the project corridor follows Minnesota State Statute Chapter 429-Local Improvements, Special Assessments. The project process steps are typically completed to take advantage of a positive bonding environment and to make full use of the construction season.

View the project process steps (PDF)

Project meetings and updates

4-7-2020 (6-8 P.M.) - Ordering Preparation of Feasibility Report - City Hall Council Chambers - 801 Washington Street Power Point Presentation

Newsletters

Project updates

10-2-20
10-9-20

Maps, plans and files