2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project Update: 05/25/2018

Formatted HTML message

Notify Me Banner
Stage 1- Division Street from Sixth Street to Eight Street
Good weather for the majority of the week allowed for quite a bit of progress again this week.  Utility crews completed the mainline sanitary sewer installations on all of Stage 1 this week.  They also worked on service installations to individual properties.  Plumbing crews were on-site late in the week to get all properties hooked up to temporary water so the existing watermain system can be shut down and taken out of service.  Utility crews also began storm sewer installations late in the week.

Next week, Utility Crews expect to complete the remaining individual service connections to each individual property.  This will involve some water shutdowns for a few properties.  Staff will be working on a shutdown plan with those properties individually.  Utility crews also expect to complete the testing on the new watermain system, and get all properties switched over to the new system.  Additionally, storm sewer installations will continue next week. 

Stage 2 - Seventh Street from Water Street to Washington Street
No work is scheduled for Stage 2 next week.

Stage 3 - Washington Street Mill and Overlay and Parking Lot Construction
No work is scheduled on Stage 3 next week.

Nate Becker, City of Northfield will be the project representative.  Nate can be reached by phone at (507) 291-6490 or via email at Nate.Becker@ci.northfield.mn.us

Please feel free to visit the 2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1140/2018-Division-St-7th-St-and-Washington-S

Thanks, and try to stay cool this Memorial Weekend!


Plain text message

Stage 1- Division Street from Sixth Street to Eight Street
Good weather for the majority of the week allowed for quite a bit of progress again this week. Utility crews completed the mainline sanitary sewer installations on all of Stage 1 this week. They also worked on service installations to individual properties. Plumbing crews were on-site late in the week to get all properties hooked up to temporary water so the existing watermain system can be shut down and taken out of service. Utility crews also began storm sewer installations late in the week.

Next week, Utility Crews expect to complete the remaining individual service connections to each individual property. This will involve some water shutdowns for a few properties. Staff will be working on a shutdown plan with those properties individually. Utility crews also expect to complete the testing on the new watermain system, and get all properties switched over to the new system. Additionally, storm sewer installations will continue next week.

Stage 2 - Seventh Street from Water Street to Washington Street
No work is scheduled for Stage 2 next week.

Stage 3 - Washington Street Mill and Overlay and Parking Lot Construction
No work is scheduled on Stage 3 next week.

Nate Becker, City of Northfield will be the project representative. Nate can be reached by phone at (507) 291-6490 or via email at Nate.Becker@ci.northfield.mn.us

Please feel free to visit the 2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1140/2018-Division-St-7th-St-and-Washington-S

Thanks, and try to stay cool this Memorial Weekend!

SMS message

Please see updates for the 2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project: https://bit.ly/2KTYzz6