Division and 7th Reconstruction/Washington St. Mill and Overlay
Sent By:
(Automatically Sent By Website)
Send Date:
6/8/2018 7:16:41 AM
Email Subject:
2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project Update: 06/08/2018

Formatted HTML message

Notify Me Banner
Stage 1- Division Street from Sixth Street to Eight Street
Crews made substantial progress on the jobsite this week.  Utility crews finished up the remaining individual service connections this week, and have all properties on Stage 1 hooked up to the new watermain and sanitary sewer systems.  Utility crews completed the remaining storm sewer on Stage 1 also this week.  Grading crews and concrete crews mobilized to the site this week.  Grading crews worked on removing the existing concrete walks and beginning the process of subcutting the existing road base material in preparation of placing the new select granular and gravel road base.  Concrete crews began working on curb and gutter and crosswalk installations in the Sixth Street and Division Street intersection.

Next week, grading crews will continue to work on subcutting, and placing the new select granular and gravel road base.  Concrete crews anticipate completing the crosswalks, curb and gutter, and sidewalks in the Sixth Street and Division Street intersection.  Additional concrete crews are expected to be on-site next week to begin the stone monument installations along the Econo Foods parking lot.

Stage 2 - Seventh Street from Water Street to Washington Street
No work is scheduled for Stage 2 next week.

Stage 3 - Washington Street Mill and Overlay and Parking Lot Construction
No work is scheduled on Stage 3 next week.

Nate Becker, City of Northfield will be the project representative.  Nate can be reached by phone at (507) 291-6490 or via email at Nate.Becker@ci.northfield.mn.us

Please feel free to visit the 2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1140/2018-Division-St-7th-St-and-Washington-S'

Have a great weekend!




Plain text message

Stage 1- Division Street from Sixth Street to Eight Street
Crews made substantial progress on the jobsite this week. Utility crews finished up the remaining individual service connections this week, and have all properties on Stage 1 hooked up to the new watermain and sanitary sewer systems. Utility crews completed the remaining storm sewer on Stage 1 also this week. Grading crews and concrete crews mobilized to the site this week. Grading crews worked on removing the existing concrete walks and beginning the process of subcutting the existing road base material in preparation of placing the new select granular and gravel road base. Concrete crews began working on curb and gutter and crosswalk installations in the Sixth Street and Division Street intersection.

Next week, grading crews will continue to work on subcutting, and placing the new select granular and gravel road base. Concrete crews anticipate completing the crosswalks, curb and gutter, and sidewalks in the Sixth Street and Division Street intersection. Additional concrete crews are expected to be on-site next week to begin the stone monument installations along the Econo Foods parking lot.

Stage 2 - Seventh Street from Water Street to Washington Street
No work is scheduled for Stage 2 next week.

Stage 3 - Washington Street Mill and Overlay and Parking Lot Construction
No work is scheduled on Stage 3 next week.

Nate Becker, City of Northfield will be the project representative. Nate can be reached by phone at (507) 291-6490 or via email at Nate.Becker@ci.northfield.mn.us

Please feel free to visit the 2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1140/2018-Division-St-7th-St-and-Washington-S'

Have a great weekend!

SMS message

Please see updates for the 2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project: https://bit.ly/2xQV4I8