2019 Street Reclamation Project Update: 05/03/2019

Formatted HTML message

Notify Me Banner
Staff held a bid opening on Thursday April 25 for the 2019 Street Reclamation Project.  No bids were received for the Construction Project.  Staff and the Design Engineer had numerous conversation with potential bidders to discuss reasons no bids were received.  The common theme from the Contractors was the proposed schedule to complete the project within the timelines set forth for the 2019 Construction Season were not realistic.

Staff, along  with the Design Engineer have suggested a new schedule based on comments from conversations with potential bidders.  The new schedule would require only the north portion of the reclamation project to be completed from July 2019 - November 2019.  The roads included in this proposal include:
  • Blue Stem Court
  • Covey Court
  • Eklund Court
  • Grundhoefer Court
  • Hackerson Court
  • Kimble Court
  • Nelson Court
  • Simione Court
  • Wilson Court
  • Zanmiller Drive from Meldahl Lane to Gill Lane
  • Gill Lane from Zanmiller Drive to Lockwood Drive
  • Lockwood Drive from Meldahl Lane to Gill Lane
The new proposal would also require the southern portions of the project to be completed from May 2020 - September 2020.  The roads included in this proposal include:
  • Orchard Street from Third Street to Fifth Street
  • Plum Street from Third Street to Fifth Street
  • Poplar Street from Fourth Street to Fifth Street
  • Forest Avenue from Lincoln Street to Fifth Street
  • Forest Avenue Loop
  • Third Street from Railroad Tracks to Forest Avenue
  • Fourth Street from Odd Fellows Lane to Poplar Street
Staff, along with the Design Engineer believe that this proposed schedule will allow flexibility for already busy Contractors to complete the project.  If approved by City Council, a June 6, 2019 bid opening has been proposed.

Aside from the construction portion of the project, the Assessment Hearing is scheduled for the May 21, 2019 City Council meeting.  Staff mailed out Hearing Notices this week along with additional assessment information for properties proposed for assessments.  This hearing will give an opportunity for property owners to discuss their proposed assessments during the Public Hearing.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great day!





Plain text message

Staff held a bid opening on Thursday April 25 for the 2019 Street Reclamation Project. No bids were received for the Construction Project. Staff and the Design Engineer had numerous conversation with potential bidders to discuss reasons no bids were received. The common theme from the Contractors was the proposed schedule to complete the project within the timelines set forth for the 2019 Construction Season were not realistic.

Staff, along with the Design Engineer have suggested a new schedule based on comments from conversations with potential bidders. The new schedule would require only the north portion of the reclamation project to be completed from July 2019 - November 2019. The roads included in this proposal include:

Blue Stem Court
Covey Court
Eklund Court
Grundhoefer Court
Hackerson Court
Kimble Court
Nelson Court
Simione Court
Wilson Court
Zanmiller Drive from Meldahl Lane to Gill Lane
Gill Lane from Zanmiller Drive to Lockwood Drive
Lockwood Drive from Meldahl Lane to Gill Lane

The new proposal would also require the southern portions of the project to be completed from May 2020 - September 2020. The roads included in this proposal include:

Orchard Street from Third Street to Fifth Street
Plum Street from Third Street to Fifth Street
Poplar Street from Fourth Street to Fifth Street
Forest Avenue from Lincoln Street to Fifth Street
Forest Avenue Loop
Third Street from Railroad Tracks to Forest Avenue
Fourth Street from Odd Fellows Lane to Poplar Street

Staff, along with the Design Engineer believe that this proposed schedule will allow flexibility for already busy Contractors to complete the project. If approved by City Council, a June 6, 2019 bid opening has been proposed.

Aside from the construction portion of the project, the Assessment Hearing is scheduled for the May 21, 2019 City Council meeting. Staff mailed out Hearing Notices this week along with additional assessment information for properties proposed for assessments. This hearing will give an opportunity for property owners to discuss their proposed assessments during the Public Hearing.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great day!

SMS message

Please see updates for the 2019 Street Reclamation Project: https://bit.ly/2vDrjWY