Email Subject:
2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project Update: 04/26/2018

Formatted HTML message

Notify Me Banner
City Council awarded the Construction Contract at the April 17, 2018 City Council meeting to Swenke Ims Contracting LLC from Kasson, MN.  Staff held the preconstruction conference this week, and crews are expected to start on Stage 1 on Monday April 30, 2018.  Staff has also been conducting property owner meeting with all properties on Stage 1 and Stage 2 this week.  Please see the proposed schedule for each individual construction stage below:

Stage 1- Division Street from Sixth Street to Eight Street
Staff held individual meetings with the affected property owners on Stage 1 late this week to discuss the proposed schedule submitted by the contractor, and the affect to each individual property.  Crews expect to begin work on Stage 1 on Monday April 30, 2018.  Work expected next week include the closure of Division Street to thru traffic from Sixth Street to Eighth Street first thing Monday morning.  A detour will be posted around the closure utilizing Washington Street.  Additional work included next week will be bituminous and concrete street removals, curb and gutter removals, and driveway removals.  Crews expect to begin utility installations the week of May 7.

Stage 2 - Seventh Street from Water Street to Washington Street
Staff also held individual meetings with the affected property owners on Stage 2 late this week to discuss the proposed schedule submitted by the contractor, and the affect to each individual property.  The contractor expects to begin work on Stage 2 sometime mid-July, when Stage 1 is complete.

Stage 3 - Washington Street Mill and Overlay and Parking Lot Construction
No work is scheduled on Stage 3 until late July.  Staff will send letters requesting property owner meetings on Stage 3 once construction is closer to beginning.

Please check your mail later this weekend, a newsletter will be mailed to all property owners on the entire project corridor with a more detailed proposed project schedule.

Nate Becker, City of Northfield will be the project representative.  Nate can be reached by phone at (507) 291-6490 or via email at Nate.Becker@ci.northfield.mn.us

Please feel free to visit the 2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1140/2018-Division-St-7th-St-and-Washington-S

Thanks, and have a great day!


Plain text message

City Council awarded the Construction Contract at the April 17, 2018 City Council meeting to Swenke Ims Contracting LLC from Kasson, MN. Staff held the preconstruction conference this week, and crews are expected to start on Stage 1 on Monday April 30, 2018. Staff has also been conducting property owner meeting with all properties on Stage 1 and Stage 2 this week. Please see the proposed schedule for each individual construction stage below:

Stage 1- Division Street from Sixth Street to Eight Street
Staff held individual meetings with the affected property owners on Stage 1 late this week to discuss the proposed schedule submitted by the contractor, and the affect to each individual property. Crews expect to begin work on Stage 1 on Monday April 30, 2018. Work expected next week include the closure of Division Street to thru traffic from Sixth Street to Eighth Street first thing Monday morning. A detour will be posted around the closure utilizing Washington Street. Additional work included next week will be bituminous and concrete street removals, curb and gutter removals, and driveway removals. Crews expect to begin utility installations the week of May 7.

Stage 2 - Seventh Street from Water Street to Washington Street
Staff also held individual meetings with the affected property owners on Stage 2 late this week to discuss the proposed schedule submitted by the contractor, and the affect to each individual property. The contractor expects to begin work on Stage 2 sometime mid-July, when Stage 1 is complete.

Stage 3 - Washington Street Mill and Overlay and Parking Lot Construction
No work is scheduled on Stage 3 until late July. Staff will send letters requesting property owner meetings on Stage 3 once construction is closer to beginning.

Please check your mail later this weekend, a newsletter will be mailed to all property owners on the entire project corridor with a more detailed proposed project schedule.

Nate Becker, City of Northfield will be the project representative. Nate can be reached by phone at (507) 291-6490 or via email at Nate.Becker@ci.northfield.mn.us

Please feel free to visit the 2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1140/2018-Division-St-7th-St-and-Washington-S

Thanks, and have a great day!

SMS message

Please see updates for the 2018 Division and Seventh Street Reconstruction/Washington Street Mill and Overlay Project: https://bit.ly/2vVWHTZ