8/16/2019 6:27:46 AM
Email Subject:
Spring Creek Road Reconstruction Project Update 08/16/2019

Formatted HTML message

Notify Me Banner Spring Creek Road Reconstruction Project Update
Phase 1 - Superior Drive to Huron Court
Curb and gutter crews were on-site this week to pour the new curb and gutter on Phase 1 from Jefferson Parkway south to Superior Drive.  Xcel energy was also on-site and finished the power pole relocations on all of Phase 1.

Next week, grading crews will continue working on ditch grading on all of Phase 1.

Phase 2 - Huron Court to the North Project Boundary
Grading crews continued sub-cutting and placing the new granular base on Phase 2 this week.  Xcel Energy was also on-site, and completed the remaining pole relocations on Phase 2.

Next week, grading crews expect to complete the sub-cutting and granular placement on Phase 2.  Grading crews will then concentrate on ditch grading along the entire project corridor. 
      
Please contact the Engineering Department for any questions at (507) 645-3020.

Please visit the Spring Creek Road Reconstruction Website for additional information:
https://www.ci.northfield.mn.us/1141/Spring-Creek-RoadHall-Avenue-Reconstruct

Have a great weekend!
 
           


   
           


          
                      

 

           


           

         



                                 

           
           



Plain text message

Spring Creek Road Reconstruction Project Update
Phase 1 - Superior Drive to Huron Court
Curb and gutter crews were on-site this week to pour the new curb and gutter on Phase 1 from Jefferson Parkway south to Superior Drive. Xcel energy was also on-site and finished the power pole relocations on all of Phase 1.

Next week, grading crews will continue working on ditch grading on all of Phase 1.

Phase 2 - Huron Court to the North Project Boundary
Grading crews continued sub-cutting and placing the new granular base on Phase 2 this week. Xcel Energy was also on-site, and completed the remaining pole relocations on Phase 2.

Next week, grading crews expect to complete the sub-cutting and granular placement on Phase 2. Grading crews will then concentrate on ditch grading along the entire project corridor.

Please contact the Engineering Department for any questions at (507) 645-3020.

Please visit the Spring Creek Road Reconstruction Website for additional information:

https://www.ci.northfield.mn.us/1141/Spring-Creek-RoadHall-Avenue-Reconstruct

Have a great weekend!