2019 Street Reclamation Project
Sent By:
(Automatically Sent By Website)
Send Date:
8/23/2019 8:18:05 AM
Email Subject:
2019 Street Reclamation Project Update: 08/23/2019

Formatted HTML message

Notify Me Banner

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court

Removal crews were on-site this week working on tree removals, and curb and gutter removals on all of Phase 1.  Crews also installed inlet protection on all existing storm sewer structures to capture any sediment that may run off during construction.

Next week, removal crews anticipate removing the remaining curb and gutter, and driveway aprons scheduled for replacement.  Grading crews will also be on-site working on grading out for the new sidewalk on the east side of Zanmiller Drive from Gill Lane to Meldahl Lane.  Later in the week, concrete crews are scheduled to be on-site to begin pouring the new curb and gutter, driveway aprons, sidewalks, and pedestrian ramps on all of Phase 1.


Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street
Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great weekend!




   

Plain text message

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court

Removal crews were on-site this week working on tree removals, and curb and gutter removals on all of Phase 1. Crews also installed inlet protection on all existing storm sewer structures to capture any sediment that may run off during construction.

Next week, removal crews anticipate removing the remaining curb and gutter, and driveway aprons scheduled for replacement. Grading crews will also be on-site working on grading out for the new sidewalk on the east side of Zanmiller Drive from Gill Lane to Meldahl Lane. Later in the week, concrete crews are scheduled to be on-site to begin pouring the new curb and gutter, driveway aprons, sidewalks, and pedestrian ramps on all of Phase 1.

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street
Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great weekend!