2019 Street Reclamation Project
Sent By:
(Automatically Sent By Website)
Send Date:
8/29/2019 3:34:07 PM
Email Subject:
2019 Street Reclamation Project Update: 08/29/2019

Formatted HTML message

Notify Me Banner

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court

Removal/Grading crews were on-site the majority of the week removing existing curb and gutter and sidewalk that are scheduled for replacement.  Crews also worked on grading out new sidewalk areas along Zanmiller Drive.  Crews also repaired existing storm sewer structures along the project corridor. 

Next week, concrete crews are scheduled to be on-site to begin pouring the new curb and gutter and sidewalks.  Removal crews will also begin removing driveway aprons along the project corridor.  City Staff will notify properties early next week if your driveway is scheduled for removal/replacement.  If your driveway is scheduled for removal, residents can anticipate a 5-10 day closure of your driveway to allow the installation and proper curing of the new concrete.  Additionally, retaining wall crews will be on-site to begin retaining wall installations that have been identified along the project corridor.


Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street
Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great Labor Day Weekend!




   

Plain text message

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court

Removal/Grading crews were on-site the majority of the week removing existing curb and gutter and sidewalk that are scheduled for replacement. Crews also worked on grading out new sidewalk areas along Zanmiller Drive. Crews also repaired existing storm sewer structures along the project corridor.

Next week, concrete crews are scheduled to be on-site to begin pouring the new curb and gutter and sidewalks. Removal crews will also begin removing driveway aprons along the project corridor. City Staff will notify properties early next week if your driveway is scheduled for removal/replacement. If your driveway is scheduled for removal, residents can anticipate a 5-10 day closure of your driveway to allow the installation and proper curing of the new concrete. Additionally, retaining wall crews will be on-site to begin retaining wall installations that have been identified along the project corridor.

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street

Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:
https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great Labor Day Weekend!

SMS message

Please see updates for the 2019 Street Reclamation Project: https://bit.ly/32gX6LZ