2019 Street Reclamation Project
Sent By:
(Automatically Sent By Website)
Send Date:
9/6/2019 7:45:31 AM
Email Subject:
2019 Street Reclamation Project Update: 09/06/2019

Formatted HTML message

Notify Me Banner

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court

Concrete crews were on-site the majority of the week to begin pouring curb and gutter, sidewalks, and driveway aprons on all of Phase 1.  Retaining wall crews were also on-site to work on retaining walls on Zanmiller Drive.

Next week, concrete crews will continue to pouring curb and gutter, sidewalks, and driveway aprons on all of Phase 1.  Crews anticipate completing all of the concrete work by the end of next week, weather permitting.  Grading crews will also be on-site backfilling boulevards with new topsoil on all areas of Phase 1.  Grading crews will also work on backfilling the street areas with gravel where curb and gutter replacements occurred.  Just a quick note, pavement reclamation for all of Phase 1 is scheduled for the week of September 16.

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street
Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great DJJD weekend!




   

Plain text message

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court

Concrete crews were on-site the majority of the week to begin pouring curb and gutter, sidewalks, and driveway aprons on all of Phase 1. Retaining wall crews were also on-site to work on retaining walls on Zanmiller Drive.

Next week, concrete crews will continue to pouring curb and gutter, sidewalks, and driveway aprons on all of Phase 1. Crews anticipate completing all of the concrete work by the end of next week, weather permitting. Grading crews will also be on-site backfilling boulevards with new topsoil on all areas of Phase 1. Grading crews will also work on backfilling the street areas with gravel where curb and gutter replacements occurred. Just a quick note, pavement reclamation for all of Phase 1 is scheduled for the week of September 16.

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street

Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great DJJD weekend!

SMS message

Please see updates for the 2019 Street Reclamation Project: https://bit.ly/2lAqDQI