2019 Street Reclamation Project
Sent By:
(Automatically Sent By Website)
Send Date:
9/13/2019 6:55:52 AM
Email Subject:
2019 Street Reclamation Project Update: 09/13/2019

Formatted HTML message

Notify Me Banner

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court

Concrete crews completed the remaining curb and gutter, sidewalks and driveway aprons early in the week on Phase 1.  Rain hampered progress on the job for the remainder of the week.  Concrete crews are expected to be on-site today to complete the remaining pedestrian ramps on Phase 1.

Next week, reclamation crews will be on-site late in the week to perform the pavement reclamation on all of Phase 1, including Blue Stem Court.  Utility crews will also be on-site to install the drain tile on Blue Stem Court and Zanmiller Drive once the pavement reclamation is complete.  Motorists can expect traffic delays during the pavement reclamation process. 

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street
Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great weekend!




   

Plain text message

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court

Concrete crews completed the remaining curb and gutter, sidewalks and driveway aprons early in the week on Phase 1. Rain hampered progress on the job for the remainder of the week. Concrete crews are expected to be on-site today to complete the remaining pedestrian ramps on all of Phase 1.

Next week, reclamation crews will be on-site late in the week to perform the pavement reclamation on all of Phase 1, including Blue Stem Court. Utility crews will also be on-site to install the drain tile on Blue Stem Court and Zanmiller Drive once the pavement reclamation is complete. Motorists can expect traffic delays during the pavement reclamation process.

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street

Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project


Thanks, and have a great weekend!

SMS message

Please see updates for the 2019 Street Reclamation Project: https://bit.ly/2lP77QB