Spring Creek Road Reconstruction Project Update 09/13/2019

Formatted HTML message

Notify Me Banner Spring Creek Road Reconstruction Project Update
 Rain hampered progress on the jobsite this week.  Small utility crews from Century Link were on-site this week to complete their relocation of their facilities along the entire project corridor.  Grading crews were on-site late in the week raising manholes and gate valves along the project corridor.

Next week, small utility crews are expected to complete their relocations, and the remaining ditch grading can occur once the site dries up.  Landscape crews, which were rained out this week, will be on-site next week to plant trees along the project corridor.  Paving of the 1st lift of bituminous is tentatively scheduled for the week of September 23.
      
Please contact the Engineering Department for any questions at (507) 645-3020.

Please visit the Spring Creek Road Reconstruction Website for additional information:
https://www.ci.northfield.mn.us/1141/Spring-Creek-RoadHall-Avenue-Reconstruct

           
 
           


   
           


          
                      

 

           


           

         



                                 

           
           



Plain text message

Spring Creek Road Reconstruction Project Update
Rain hampered progress on the jobsite this week. Small utility crews from Century Link were on-site this week to complete their relocation of their facilities along the entire project corridor. Grading crews were on-site late in the week raising manholes and gate valves along the project corridor.

Next week, small utility crews are expected to complete their relocations, and the remaining ditch grading can occur once the site dries up. Landscape crews, which were rained out this week, will be on-site next week to plant trees along the project corridor. Paving of the 1st lift of bituminous is tentatively scheduled for the week of September 23.

Please contact the Engineering Department for any questions at (507) 645-3020.

Please visit the Spring Creek Road Reconstruction Website for additional information:

https://www.ci.northfield.mn.us/1141/Spring-Creek-RoadHall-Avenue-Reconstruct

SMS message

Please see updates for the Woodley Street Reconstruction Project: https://bit.ly/2lUSIC8