Available Lists
Sender Name:
Spring Creek Road Reconstruction Project
Sent By:
(Automatically Sent By Website)
Send Date:
9/20/2019 6:34:47 AM
Email Subject:
Spring Creek Road Reconstruction Project Update 09/20/2019

Formatted HTML message

Notify Me Banner Spring Creek Road Reconstruction Project Update
 Landscape crews were on-site this week to plant new boulevard trees along the entire project corridor.  Grading crews were also on-site late in the week, grading out driveways and the remaining ditch areas.  Grading crews also provided the final touches on the gravel base in preparation of paving.  Paving is scheduled for tomorrow (Saturday) for the entire project, weather depending.  Paving will be moved to Monday, if it does rain tomorrow.

Next week, grading crews are expected to complete the remaining ditch grading.  Landscape crews are also scheduled to be on-site to install sod and seeding along the entire project corridor.  Traffic control crews are also scheduled to be on-site to install the new traffic control signs along the project as well.
      
Please contact the Engineering Department for any questions at (507) 645-3020.

Please visit the Spring Creek Road Reconstruction Website for additional information:
https://www.ci.northfield.mn.us/1141/Spring-Creek-RoadHall-Avenue-Reconstruct

           
 
           


   
           


          
                      

 

           


           

         



                                 

           
           



Plain text message

Spring Creek Road Reconstruction Project Update
Landscape crews were on-site this week to plant new boulevard trees along the entire project corridor. Grading crews were also on-site late in the week, grading out driveways and the remaining ditch areas. Grading crews also provided the final touches on the gravel base in preparation of paving. Paving is scheduled for tomorrow (Saturday) for the entire project, weather depending. Paving will be moved to Monday, if it does rain tomorrow.

Next week, grading crews are expected to complete the remaining ditch grading. Landscape crews are also scheduled to be on-site to install sod and seeding along the entire project corridor. Traffic control crews are also scheduled to be on-site to install the new traffic control signs along the project as well.

Please contact the Engineering Department for any questions at (507) 645-3020.

Please visit the Spring Creek Road Reconstruction Website for additional information:
https://www.ci.northfield.mn.us/1141/Spring-Creek-RoadHall-Avenue-Reconstruct