2019 Street Reclamation Project
Sent By:
(Automatically Sent By Website)
Send Date:
10/4/2019 6:50:28 AM
Email Subject:
2019 Street Reclamation Project Update: 10/4/2019

Formatted HTML message

Notify Me Banner

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court
Milling crews are currently on-site milling off the excess reclaim on Phase 1.  Crews expect to complete the milling operations by the end of the day today.  Grading crews will be on-site today working on grading the existing reclaim base.  Additional rain is predicted tonight/tomorrow which more than likely will make the reclaim base very saturated.  Please use caution driving on the reclaimed road base. 

Next week, grading crews are scheduled to remain on-site to grade the existing reclaim base, and prepare it for the new asphalt  pavement.  Paving crews are currently scheduled to be on-site late next week to begin paving the base course asphalt pavement on all of Phase 1.  This paving schedule is tentative, and can be greatly influenced by the upcoming weather.  Additional updates will be sent out once the schedule has been verified.
 

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street
Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great weekend!




   

Plain text message

Phase 1

Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court

Milling crews are currently on-site milling off the excess reclaim on Phase 1. Crews expect to complete the milling operations by the end of the day today. Grading crews will be on-site today working on grading the existing reclaim base. Additional rain is predicted tonight/tomorrow which more than likely will make the reclaim base very saturated. Please use caution driving on the reclaimed road base.

Next week, grading crews are scheduled to remain on-site to grade the existing reclaim base, and prepare it for the new asphalt pavement. Paving crews are currently scheduled to be on-site late next week to begin paving the base course asphalt pavement on all of Phase 1. This paving schedule is tentative, and can be greatly influenced by the upcoming weather. Additional updates will be sent out once the schedule has been verified.

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street

Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great weekend!

SMS message

Please see updates for the 2019 Street Reclamation Project: https://bit.ly/2Ojn7q4