2019 Street Reclamation Project
Sent By:
(Automatically Sent By Website)
Send Date:
10/11/2019 6:56:53 AM
Email Subject:
2019 Street Reclamation Project Update: 10/11/2019

Formatted HTML message

Notify Me Banner

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court
Grading crews worked on tolerancing and drying out the reclaim base preparing the roads for paving.  Unfortunately rain has hampered any substantial progress that we made earlier in the week.  Paving was scheduled for today and tomorrow, but that has been pushed back until the site can dry out, and be suitable for paving.

Next week, grading crews will be back on-site again to continue drying out and tolerancing the reclaim base in preparation of paving as weather allows.
 
Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street
Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great weekend!




   

Plain text message

Phase 1

Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court

Grading crews worked on tolerancing and drying out the reclaim base preparing the roads for paving. Unfortunately rain has hampered any substantial progress that we made earlier in the week. Paving was scheduled for today and tomorrow, but that has been pushed back until the site can dry out, and be suitable for paving.

Next week, grading crews will be back on-site again to continue drying out and tolerancing the reclaim base in preparation of paving as weather allows.

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street

Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great weekend!

SMS message

Please see updates for the 2019 Street Reclamation Project: https://bit.ly/2Vyj2zS