2019 Street Reclamation Project Update: 10/24/2019

Formatted HTML message

Notify Me Banner

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court
Grading crews are working to dry out the reclamation base again after rains earlier in the week.  Paving is scheduled and confirmed to begin on Saturday, October 26, and will be finished on Monday October 28.  No paving will be completed on Sunday.  We ask that residents refrain from parking on the streets on Saturday and Monday, so paving crews can complete the entire paving operation.  The City of Northfield appreciates your patience while we navigate the extremely wet weather we have experienced the past 3-4 weeks.

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street
Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great weekend!




   

Plain text message

Phase 1
Simione Court, Nelson Court, Kimble Court, Hackerson Court, Grundhoefer Court, Eklund Court, Covey Court, Lockwood Drive, Gill Lane, Zanmiller Drive, and Bluestem Court
Grading crews are working to dry out the reclamation base again after rains earlier in the week. Paving is scheduled and confirmed to begin on Saturday, October 26, and will be finished on Monday October 28. No paving will be completed on Sunday. We ask that residents refrain from parking on the streets on Saturday and Monday, so paving crews can complete the entire paving operation. The City of Northfield appreciates your patience while we navigate the extremely wet weather we have experienced the past 3-4 weeks.

Phase 2
Third Street, Fourth Street, Armstrong Road, Forest Avenue, Forest Avenue Loop, Poplar Street, Plum Street, and Orchard Street

Construction is scheduled for the Spring of 2020.

Please feel free to visit the 2019 Street Reclamation Project website at the link below for additional information regarding the project:

https://www.ci.northfield.mn.us/1239/2019-Street-Reclamation-Project

Thanks, and have a great weekend!

SMS message

Please see updates for the 2019 Street Reclamation Project: https://bit.ly/2p9kKvT